To deliver computing power, Oracle uses trucks to transport natural gas to power its data centers

To deliver computing power, Oracle uses trucks to transport natural gas to power its data centers

华尔街见闻华尔街见闻2026/10/08 23:32
Show original
By:华尔街见闻

To address pipeline delays in AI data center construction, Oracle has adopted an unconventional energy supply method by transporting compressed natural gas via trucks, which has already been implemented in Utah and Texas, and is also being considered for the "Project Jupiter" in New Mexico. However, this solution costs four times as much as pipeline natural gas and is limited in scale, covering only a small fraction of the project's total capacity.

In order to deliver its AI data centers on schedule, Oracle has adopted unconventional energy supply methods to cope with pipeline delays, yet high costs and scalability bottlenecks remain significant concerns.

On October 8, Bloomberg reported that Oracle is using trucks to transport compressed natural gas to maintain the construction and operation schedules of several AI data centers, seeking to avoid time losses caused by pipeline infrastructure delays.

This unorthodox strategy has already been implemented in Utah and Texas, and is under consideration for key projects in New Mexico. Oracle currently has negative free cash flow, and it is expected to remain under pressure until more AI data centers are completed and operational.

Oracle's stock price closed down 5.5% on Thursday at $135.69, its largest single-day drop since July 16.

To deliver computing power, Oracle uses trucks to transport natural gas to power its data centers image 0

Meanwhile, Bloom Energy—which has a fuel cell collaboration with Oracle—saw its share price plunge more than 6% on the same day, as market concerns mounted over Oracle’s data center expansion pace and the future of related partnerships.

To deliver computing power, Oracle uses trucks to transport natural gas to power its data centers image 1

Truck-based Gas Supply Has Precedents: Utah and Texas Were First

This is not Oracle’s first attempt at such measures.

According to sources cited in reports, in the data center project in the suburbs of Salt Lake City, Oracle has sustained normal progress for over a year by having natural gas delivered by truck, with services provided by Certarus, a subsidiary of Superior Plus.

Certarus noted that timelines for connecting data centers to both pipelines and the power grid are extending, “creating rapidly increasing demand for energy solutions that can be rapidly deployed and scaled flexibly.”

At the OpenAI data center campus project in Shackelford County, Texas, Oracle adopted the same approach, with VoltaGrid LLC as the supplier. Oracle posted on social media:

Thanks to the VoltaGrid team for finding a cost-effective power supply solution, ensuring customers are able to use OCI (Oracle Cloud Infrastructure) computing power on schedule.

The highest-pressure bottleneck is in New Mexico.

Wallstreet Insight reported that the data center project code-named "Project Jupiter" is facing serious pipeline delays. Pipeline operator Energy Transfer LP had its original plan rejected by New Mexico regulators and must now redesign the route, pushing the expected operational launch from this summer to next year.

To keep the project on schedule, Oracle is considering trucking compressed natural gas to the data center, allowing early-stage operations to begin before the pipeline is fully connected. The urgency is apparent: Last month, Oracle issued a force majeure notice to the project developer. Should delays persist, this move may exempt the company from some payment obligations.

High Costs and Scalability Limits: Not a Long-term Solution

Trucking in compressed natural gas is not a cheap solution.

Jack Weixel, Senior Director of Energy Analysis at East Daley Analytics, estimates that—factoring in labor, specialized equipment, and vehicle fuel costs—the price of truck-delivered compressed natural gas is about four times that of natural gas at major pipeline hubs.

Natural gas must first be extracted from pipelines, compressed and loaded onto trucks, then transported for several hours before being decompressed and injected into generators. For continuously operating data centers, this means non-stop truck dispatches around the clock.

Scalability constraints are also significant.

SemiAnalysis analyst Ellie Holbrook calculates that if Oracle used compressed natural gas trucks to provide 100 megawatts of power for "Project Jupiter," this would represent only about 4% of the project’s planned 2.45-gigawatt total capacity, with each large truck delivering only about 40 minutes’ worth of power—which means dozens of truck trips would be required daily for continuous supply.

For this reason, compressed natural gas trucking has historically been confined to remote industrial settings such as mining or oil drilling that are far from grid connections. However, for Oracle—which has made commitments to clients including OpenAI and urgently needs to deliver computing power on schedule—this may be the most viable transitional solution under current conditions.

0
0

Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.

Understand the market, then trade.
Bitget offers one-stop trading for cryptocurrencies, stocks, and gold.
Trade now!

You may also like

ECB Presidential Contest Centers on Crisis Management: French Debt Risk Becomes the Touchstone

The competition for the position of President of the European Central Bank is increasingly centered on a key question: which candidate is best equipped to deal with the "vigilantes" of the bond market? As France's debt issues revive memories of turmoil in the Eurozone and the current president, Christine Lagarde, prepares to step down early, Dutchman Klaas Knot and Spaniard Pablo Hernández de Cos may soon take over amid financial turbulence.

智通财经•2026/10/25 10:41
ECB Presidential Contest Centers on Crisis Management: French Debt Risk Becomes the Touchstone

Deutsche Bank, which "accurately called the top" two weeks ago: Tech stocks need to "fall another 5%" to reach the "long-term trend bottom"

After Deutsche Bank downgraded its rating on US tech and large-cap growth stocks two weeks ago, tech stocks have underperformed the rest of the S&P 500 components by 12 percentage points. However, Deutsche Bank noted that tech stocks still have about 5 percentage points of downside before reaching the bottom of their long-term trend channel. Institutional positions have been quickly cooling, and signs of outflows from the $30 billion bottom-fishing funds are beginning to appear. Going forward, earnings performance, capital flows, and external risks will determine whether the adjustment stops at structural rotation.

华尔街见闻•2026/10/25 07:21
Deutsche Bank, which "accurately called the top" two weeks ago: Tech stocks need to "fall another 5%" to reach the "long-term trend bottom"